Modernizing the Waldeck 1 Pumped Storage Power Plant-Construction of a New Pressurized Duct Power Plant

Bild Pumpspeicherkraftwerk Waldeck 1

Site

The new power station will feature a compact design and be built right on the bank of the lower basin, between the trainee workshop and the existing facility's powerhouse. This will allow us to make straight-line connections between the new unit and the existing pressurized pipelines.

 

The plot of land reserved for the construction project has a usable clearance width of 34.6 meters. The new power plant's duct has a diameter of 17 meters at generator hall level and of about 50 meters at maximum duct depth. The section of the duct located under water consists of a draft tube and a draft duct, referred to as the "gooseneck."

 

Technical Data
Waldeck I Pressurized Duct Power Station
Pump turbine (Francis turbine) 
Nominal output (turbine/pump) 70 MW
Gross drop 296.65 m
Rotational speed 500 rpm
Rotational efficiency 75%
Max. turbine throughput 28 m³/s
Max. pump throughput 24 m²/s
Runner installation depth -30 m (176 m MSL)
Motor Generator 
Three-phase synchronous machine
Nominal output (generator/motor) 80 MVA
Nominal voltage 10.5 kV
Generator Transformer 
Nominal output 80 MVA
Nominal transfer rate 110 kV/10.5 kV
Existing Plant After Overhaul 
Nominal output (turbines) 2 x 35 MW