Overhauling the Waldeck 2 Pumped Storage Power Plant - Total Project
Modernization and Performance Upgrade
Rationale for the Construction Work
The Waldeck II pumped storage power station was commissioned in 1974. Two pumped storage sets-units 5 and 6-have provided reliable service since then, generating valuable peak-load electricity with an aggregate output of 440 megawatts (MW)
After more than 32 years of service, it was high time to overhaul the entire facility for technical reasons.
Concept and Timeline
Phase 1: 2005 to 2006:
- Overhaul of the generator stator, unit 5
- Inspection of the turbine and pump, unit 5
- Inspection of four ball sliders, unit 5
- New power plant control and protection system
- Inspection of ancillary facilities
- Overhaul of the upper basin
- Overhaul of hydraulic steelwork components
Phase 2: 2007 to 2010:
- Upgrade to the fire safety and ventilation system: 2007/2008
- Inspection of the pump and turbine, unit 6: 2009/2010
- Inspection of three ball sliders, unit 6: 2009/2010
Builder-Owner and Partners
Builder-owner: E.ON Wasserkraft GmbH
Superstructure supervisor: Fichtner GmbH & Co. KG
Engineering: E.ON Engineering GmbH, EHS-Laabmayer
Building contractors: ALSTOM, ANTROK, BeKor, ARGE BuM Beton- und Monierbau und Feldhaus Bergbau, SAG, SEH-Hannover, SIEMENS, TEUPE & Söhne, VA Tech Escher Wyss, VOITH , SIEMENS HYDRO, Walo Bertschinger
Security: ESU