Overhauling the Waldeck 2 Pumped Storage Power Plant - Total Project

Modernization and Performance Upgrade

Rationale for the Construction Work

The Waldeck II pumped storage power station was commissioned in 1974. Two pumped storage sets-units 5 and 6-have provided reliable service since then, generating valuable peak-load electricity with an aggregate output of 440 megawatts (MW)

 

 

Grafik Querschnitt Pumpspeicherkraftwerke Waldeck 1 und 2

After more than 32 years of service, it was high time to overhaul the entire facility for technical reasons.

 

Concept and Timeline


Phase 1: 2005 to 2006:

  • Overhaul of the generator stator, unit 5

  • Inspection of the turbine and pump, unit 5

  • Inspection of four ball sliders, unit 5

  • New power plant control and protection system

  • Inspection of ancillary facilities

  • Overhaul of the upper basin

  • Overhaul of hydraulic steelwork components

 

Phase 2: 2007 to 2010:

  • Upgrade to the fire safety and ventilation system: 2007/2008

  • Inspection of the pump and turbine, unit 6: 2009/2010

  • Inspection of three ball sliders, unit 6: 2009/2010

 

Builder-Owner and Partners

Builder-owner: E.ON Wasserkraft GmbH

Superstructure supervisor: Fichtner GmbH & Co. KG

Engineering: E.ON Engineering GmbH, EHS-Laabmayer

Building contractors: ALSTOM, ANTROK, BeKor, ARGE BuM Beton- und Monierbau und Feldhaus Bergbau, SAG, SEH-Hannover, SIEMENS, TEUPE & Söhne, VA Tech Escher Wyss, VOITH , SIEMENS HYDRO, Walo Bertschinger


Security: ESU

 

 

 

© E.ON Wasserkraft GmbH 2008